Location
Leduc County, Alberta
Client
CKD Foods (EIA) Ltd.
Value
$305,000
Completion
April 2018
JEN COL Construction was awarded the contract to complete the fit-up of an A&W Restaurant at the Edmonton International Airport Premium Outlet Collection.
With the new mall set to open in just 60 days, JEN COL carefully planned and completed select demolition, concrete work and finishing, millwork, drywall, tile and painting, while also performing mechanical and electrical work and installing equipment. JEN COL successfully completed the fit-up in 55 days, leaving the owner with five days to stock the fridges and train staff before the grand opening of the mall.
Delivery Method
Construction Management
Architect
ONPA Architects