Construction Delivery Methods: Choosing the Right Approach for Your Project

Every successful construction project begins long before construction starts. One of the most impactful decisions you can make is in choosing the right project delivery method. 

A delivery method defines how owners, architects, engineers and contractors work together throughout planning, design and construction. It affects the entire project, shaping communication, scheduling, budget management, decision-making and the overall experiences and outcomes around your project. 

So, yes, it’s kind of a big deal. And it’s good that you’re taking a few minutes to learn about the options. 

There is no single delivery method that’s right for every project. The best choice will depend on your project’s complexity, funding, timeline, desired level of involvement and long-term objectives. 

The good news: this one post will get you closer to understanding the options and when each one makes most sense. 

At JEN COL, we’ve delivered commercial, institutional and Indigenous community projects using a variety of delivery methods across Western Canada. Our experience has shown that successful projects begin by clearly understanding the owner’s goals and assembling the right team to achieve them. 

Why Early Involvement is Key

One of the biggest misconceptions in construction is that most opportunities to manage cost happen after construction begins. In reality, the greatest opportunity to influence budget, schedule and overall value occurs much earlier, during planning and design. 

When your construction partner is involved early, they can contribute practical construction knowledge while the most consequential decisions are still being shaped. This includes evaluating constructability, refining budgets, developing realistic schedules, identifying risks and recommending alternatives before changes become increasingly expensive. 

As a project progresses, flexibility continuously decreases. Once construction begins, revisions often have wider-reaching impacts on both cost and schedule. An overly simple example is moving an interior wall. On a plan it costs very little. Once the wall is framed in place, the same change can cost thousands. Once it’s wired, drywalled, taped and painted with trim, ceiling and floor finishes in place, the cost increases substantially. Another example is using the construction team’s experience and market knowledge early to recommend alternate foundation systems, structural systems or HVAC equipment that meet the project schedule rather than delaying work while waiting for long-lead materials or equipment. 

That’s why collaborative delivery methods have become increasingly popular. They allow owners, designers and builders to work together from the outset, making informed decisions before any construction dollars are committed. 

If you’d like to learn more about how early planning influences project costs, visit our What It Costs page.

Design-Bid-Build

Design-Bid-Build is the traditional construction delivery method. 

The owner first works with an architect and consultants to complete the design. Once the drawings and specifications are finalized, contractors submit competitive bids and construction is awarded to the selected bidder. 

This approach works well when the project scope is clearly defined before construction begins and the project budget and schedule align with the completed design. Because the contractor typically joins the project after the design is complete, opportunities for construction input during design are more limited. 

Best suited for:

  • Well-defined projects
  • Traditional procurement processes
  • Owners seeking the lowest construction price through competitive bidding

Construction Management at Risk

Construction Management brings the construction team into the project much earlier. 

Rather than waiting for the design to be completed, the Construction Manager works alongside the owner, architect and consultants throughout planning and design. This collaborative approach allows construction expertise to guide budgeting, scheduling, material selection, procurement and value engineering while the project is still evolving. 

Owners remain actively involved throughout the process and can participate in key decisions, including selecting trade partners if they choose. Open-book budgeting provides transparency, while early collaboration helps balance cost, efficiency, sustainability and long-term value. Construction Management at Risk also allows the project to transition to a fixed-price contract once the design and budget have been sufficiently developed. This gives owners many of the pricing benefits of a traditional fixed-price approach while retaining the advantages of early contractor involvement, open-book transparency and collaborative decision-making throughout planning and design. 

Best suited for:

  • Complex, large or phased projects
  • Renovations
  • Projects with evolving requirements
  • Owners who value collaboration and flexibility

Design-Build

Design-Build combines design and construction into one integrated team working under a single contract with the Design-Builder. 

Instead of coordinating multiple contracts, owners work with one team responsible for delivering the project from design concept through completion. Designers and builders collaborate from the beginning, improving communication and allowing design, budgeting and construction planning to happen simultaneously. 

This integrated approach often shortens project schedules, provides earlier budget certainty and creates clear accountability throughout the project.

Best suited for:

  • Projects with clear and early defined objectives
  • Owners seeking a streamlined delivery process
  • Projects where schedule and budget certainty are priorities

Progressive Design-Build

Progressive Design-Build leverages the collaborative strengths of Design-Build while providing greater flexibility during planning. 

Rather than agreeing to a fixed construction price immediately, the owner first selects the Design-Build team based on qualifications and experience. The owner, contractor, architect and consultants then work together to develop the design, refine the schedule, establish the project budget and provide approval gates that allow the owner to pause, adjust procurement or cancel the project before committing to a final construction price if funding or project requirements change before agreeing on the final construction price. 

The progressive approach allows owners to make investment decisions at defined project gates as the design develops. Rather than committing the full construction budget upfront, costs are incurred progressively, giving the owner opportunities to assess feasibility, budget and project direction before advancing to the next stage. If the project is no longer viable, these gates can provide an off-ramp before committing to full construction. 

This collaborative process allows important decisions to be made earlier, improves cost confidence and reduces uncertainty before construction begins. 

For many complex projects, Progressive Design-Build offers an effective balance between owner involvement, collaboration and streamlined project delivery.  

Best suited for:

  • Projects where the Owner’s funding and required budgeting is not yet 100% in place or funding needs are not yet known
  • Large or technically complex projects, or projects where funding and budget approvals are still being finalized 
  • Projects with evolving scope
  • Owners seeking collaboration with a single point of responsibility 

Construction Delivery Methods at a Glance

FeatureDesign-Bid-BuildConstruction ManagementDesign-BuildProgressive Design-Build
Contractor involvementAfter design is completeEarly planning and designEarly through an integrated teamEarliest through collaborative planning
Owner involvementModerateHighModerateHigh
Budget certaintyAfter tenderRefined throughout designEarlyEstablished after approval gate through collaborative planning
FlexibilityLimited after designExcellentModerateExcellent
CollaborationModerate to LowHighHighVery High
Single point of responsibilityNoNoYesYes

Which Delivery Method is Best for Your Project?

Every project has its own distinct set of priorities. 

If your design is complete and you are confident it meets your budget and schedule expectations, and tendering is your goal, Design-Bid-Build may be the right choice. 

If your project is complex or likely to evolve during planning, Construction Management at Risk provides the flexibility to make informed decisions throughout the process. 

If you value a simplified process with one integrated team and earlier budget certainty, Design-Build offers significant advantages. 

If your project would benefit from collaborative planning before establishing the final construction price, Progressive Design-Build combines many of the strengths of both approaches. 

Another way to think about the options is to start with your priorities: 

If your priority is …Consider …
Maximum owner involvementConstruction Management
Simplifying communicationDesign-Build
Competitive tendering after completed designDesign-Bid-Build
Early collaboration with later price certaintyProgressive Design-Build

The right delivery method isn’t simply about selecting a contract. It’s about choosing the approach that best supports your project’s objectives from the very beginning.

A Unique Approach From Day One

At JEN COL, we know successful projects begin long before construction starts. 

Over nearly 50 years, we’ve learned that the very best outcomes come from understanding an owner’s objectives first, then assembling the right team and selecting the delivery method that best supports those goals. The delivery method is simply the framework that enables that collaboration. 

We work best with owners who value transparency, thoughtful planning and a shared commitment to delivering quality. Together, we solve problems early, make informed decisions and stay focused on delivering projects that meet expectations for cost, schedule, performance and long-term value. 

Every project is unique. By taking the time to understand your vision, priorities and constraints, the right delivery method often becomes much easier to identify. That’s how we consistently arrive at the outcome we pride ourselves on most:

Promise, Delivered.

JEN COL Celebrates 45th Anniversary

How to Build a Better Future: JEN COL Leads The Way.

This year marks a milestone of 45 years in business for JEN COL. Our journey began with a small project for a friend, and over the years, we have completed a wide range of projects, from building Tim Hortons to water treatment plants.

Throughout our journey, our core values have been a driving force behind our success. By putting our clients first, going above and beyond, and building strong relationships based on trust and collaboration, we’ve built a reputation for delivering the unrivaled project experience. Our commitment to embracing challenges, paying meticulous attention to details, and exceeding expectations has made us leaders in the industry. As we celebrate this milestone, we’re grateful for the opportunity to continue delivering value beyond price for our clients.

We’ve achieved many noteworthy accomplishments along the way, including:

  • More than 700 projects completed to date
  • Over 70 Indigenous projects
  • Construction of over 200 school projects in western Canada
  • Completion of more than 30 LEED-certified projects since 2004
  • Contribution to Alberta’s first-ever LEED-certified renovation project at Spruce Grove City Hall

As we reflect on our legacy, we’re grateful for the support of our team and the clients who have trusted us with their projects. We look forward to many more years of growth, innovation and excellence in building a better future.

Thank you to Business in Edmonton for featuring our 45th anniversary in their magazine. And a very special thank you to our external partners for your support and acknowledgement.

Dale Fisher Arena Groundbreaking Ceremony

Group at groundbreaking for Dale Fisher Arena.

The groundbreaking ceremony for the twinning of the Dale Fisher Arena in Devon was an immensely significant moment for the community, and it was our great honor to participate in it. We extend our sincere appreciation to the City of Devon and Parkland County for inviting us to kick off this momentous milestone.

As we gathered to witness the official start of the construction, we couldn’t help but feel an overwhelming sense of pride in being a part of this historic occasion.

What the Expansion Means for the Devon Community

At JEN COL, we firmly believe that construction is about more than just building structures. It’s about creating spaces that empower and connect communities. As construction progresses, the twin arena will promote healthy living and create lasting memories for the community.

“Today is a great day for the Town of Devon. Arenas are at the heart of our Alberta communities across the province and the Dale Fisher Arena, home to the DMHA Drillers is no exception. Recreational centers are vital to the social fabric of communities, helping to promote healthy living and serving as a meeting place for friends, families and teammates.”

Honourable Randy Boissonnault, Minister of Tourism and Associate Minister of Finance and Member of Parliament for Edmonton Centre, on behalf of the Honourable Dominic LeBlanc, Minister of Intergovernmental Affairs, Infrastructure and Communities.

Rink Expansion Details

Exciting improvements are on the horizon for the Dale Fisher Arena as construction is underway to expand the facility. The expansion will include a second full sheet of ice, new dressing rooms, and an energy-efficient ice plant. Additionally, parking will be added to the west of the arena.

The Economic Benefits of the Dale Fisher Arena Expansion

The twinning of the Dale Fisher Arena will not only enhance the size of the facility but also to significantly contribute to the overall growth and development of the community, bringing with it a plethora of exciting opportunities.

“This arena expansion means so much to our community as it will double our capacity to host large-scale tournaments and provide economic benefits with more families drawn to Devon to play in the new arena.”

Jeff Craddock, Mayor of Devon.

We are deeply honored to be part of the Dale Fisher Arena groundbreaking ceremony and expansion project. The twin ice surfaces are set to be fully completed and ready for use by mid-2024. We are eagerly anticipating presenting the new addition to the community.

Shovels are in the ground at Dale Fisher Expansion project.
Arena twinning project is underway.
Speach at Devon Arena groundbreaking ceremony.
Speach at the Dale Fisher groundbreaking.
Community gathers for Dale Fisher groundbreaking ceremony.
The community of Devon gets a second sheet of ice.
JEN COL starts construction on Dale Fisher Arena.
Devon arena groundbreaking attendance.