Location

Leduc County, Alberta

Client

CKD Foods (EIA) Ltd.

Size

38m²

Completion

April 2018

JEN COL Construction was awarded the contract to complete the fit-up of an A&W Restaurant at the Edmonton International Airport Premium Outlet Collection.

With the new mall set to open in just 60 days, JEN COL carefully planned and completed select demolition, concrete work and finishing, millwork, drywall, tile and painting, while also performing mechanical and electrical work and installing equipment. JEN COL successfully completed the fit-up in 55 days, leaving the owner with five days to stock the fridges and train staff before the grand opening of the mall.

Delivery Method

Construction Management

Architect

ONPA Architects

What our client said

JEN COL assisted in selecting the appropriate design partner to work with the franchise specifications and brought various trade partners on board who understood the scope of work and worked together to achieve the project milestones. The JEN COL team brought enthusiasm, professionalism and experience to the project and went above and beyond to ensure a successful start-up of our new location. I would not hesitate to recommend JEN COL Construction and their team for future construction projects.

Brad Schneider
President, CKD Foods Ltd.